Elsthorpe Rd - Cyclone Gabrielle Recovery
Disciplines Involved: Civil | Drainage | Landscaping | Fencing
Location: Hawke’s Bay
Client: Central Hawke’s Bay District Council
Completed: June 2025
-
This contract involved urgent remediation of rural road corridors affected by Cyclone Gabrielle, including the reconstruction of damaged slopes and restoration of stream-adjacent infrastructure. Works were delivered in an environmentally sensitive rural setting and included bulk earthworks (1,200m³ slip removal), subsoil drainage at 1.5m depth, new stormwater road crossings with large diameter pipe and manholes, and construction of swales using coconut matting for long-term erosion control.
The project also included extensive landscaping and riparian restoration, with 10,000 native plants installed. Environmental measures were proactive and practical, particularly in managing live stream flows near the construction and stockpile areas.
Toa Civil Construction worked closely with rural landowners to coordinate access and maintain operations with minimal disruption.
The project also engaged the local community, with Toa Civil Construction donating 200 native plants and inviting school children from Elsthorpe to participate in native planting—a clear demonstration of our commitment to environmental and social outcomes.
Finally, 700m of fencing was installed to protect the plantings and reinstate damaged sections.
Anderson Park
Disciplines Involved: Civil | Drainage | Landscaping
Location: Napier City
Client: Napier City Council
Completed: December 2024
-
All works to Napier City Council (NCC) COP for land development and building codes
Testing and compliance to NCC standards
Health and Safety compliance with removal of asbestos
Environment compliance to HBRC Code of Practice
Development of Erosion & Sediment control plan, installation of Sediment Retention Pond, Silt Fencing and other controls
Service trenching and duct installation
Pavement construction with subbase, basecourse, & concrete with oxide
Stormwater system to NCC code
Landscape works, grassing and planting
Mission Hills Puketitiri Road Drainage
Disciplines Involved: Civil | Drainage
Location: Napier City
Client: Carrus Group
Completed: June 2023
-
The Mission Hills Puketitiri Road project in Napier involved the delivery of essential infrastructure for a major greenfield subdivision, with works spanning stormwater and wastewater networks, bulk earthworks, service trenching, and road construction. Located along a busy arterial route, the site required careful planning, environmental compliance, and detailed coordination with Napier City Council and affected stakeholders.
The project included the construction of a stormwater detention pond, a large, engineered rock swale, and the installation of sewer, stormwater, and service infrastructure to meet Napier City Council’s development standards. A significant volume of earth was moved and compacted to NZTA F/1 standards, with all testing, CCTV, and as-builts completed to NCC requirements. Despite the range of disciplines involved, the works were successfully delivered within time, budget, and environmental expectations.